Industrial Buildings (Total number: 11)- 21.000 m²
Information about the facility
:
Oil facilities contruction in Atyrau-Kazakhstan
Total Investment Value
:
160.000.000 €
Cost of Mechanical Works
:
30.000.000 €
Cost of Electromechanical Works
:
58.250.000 €
Mechanical Works Manpower
:
450.000 man hour All Building internal & external Electromechanical Works
Scope of the Mechanical Work
:
Heating, Ventilation & Air Conditioning, Plumbing System, Automatic Fire Fighting (Sprink, fi re hose cabinet) Systems, Smoke Exhaust, Pressurization System, Center Plant and External piping system, Natural Gas System, Engineering applications for all mechanical systems, Project Materials Approvel & Procurement, Construction, TAB, Commissioning of all system and handed over the Kazakhstan local authorities.